The Crest Annex · Site update
Summarised from daily site reports up to
October 18, 2026
Seven working days, around 79 workers on site each day and 85 at the busiest. Plaster moved ahead in the staircases, corridors and lift shafts, and tiling and bathroom fittings continued across all three blocks.
Every finished floor is checked by our site engineers before it is signed off, including tile tap-tests and level checks. Any tile that does not pass is lifted and relaid. Toolbox safety talks were held every day, and no accidents were reported.