The Crest Annex · Site update

Week of 12 October 2026

Summarised from daily site reports up to

October 18, 2026

Seven working days, around 79 workers on site each day and 85 at the busiest. Plaster moved ahead in the staircases, corridors and lift shafts, and tiling and bathroom fittings continued across all three blocks.

79
Average workers on site per day
85
Most workers on a single day
7
Working days this week
Finishing
Current stage

Work this week

  • Flats: floor and bathroom tiling continued floor by floor in Blocks A, B and C.
  • Internal plaster: continued in the remaining ground-floor flats of Block B.
  • Bathroom fittings: concealed cistern tanks and diverters being fixed in the remaining flats.
  • Lift shafts: internal plaster continued on the upper floors.
  • Staircases and corridors: plaster continued.
  • Exterior: front elevation brickwork on Block C and exterior plaster continued.
  • Terrace: parapet wall plaster continued.
  • Clubhouse: brickwork continued.

Completed

  • No stages were signed off this week. Work continued on every front listed above.

Coming up next week

  • Complete lift shaft internal plaster.
  • Continue internal plaster in the remaining ground-floor flats of Block B.
  • Continue staircase and corridor plaster.
  • Continue front elevation brickwork and exterior plaster.
  • Continue tiling and bathroom fittings floor by floor.
  • Continue clubhouse brickwork.

Quality and safety

Every finished floor is checked by our site engineers before it is signed off, including tile tap-tests and level checks. Any tile that does not pass is lifted and relaid. Toolbox safety talks were held every day, and no accidents were reported.