The Crest Annex · Site update
Summarised from daily site reports up to
October 4, 2026
Seven working days, around 72 workers on site each day and 80 on Sunday. Tiling, internal plaster and bathroom fittings moved ahead across all three blocks, exterior plaster continued, and clubhouse brickwork began.
Every finished floor is checked by our site engineers before it is signed off. This week that included tile tap-tests and level checks. Any tile that does not pass is lifted and relaid. Toolbox safety talks were held every day, and no accidents were reported.
Fewer workers on 2 October because of the Gandhi Jayanti public holiday.