The Crest Annex · Site update

Week of 5 October 2026

Summarised from daily site reports up to

October 11, 2026

Seven working days, around 76 workers on site each day and 82 at the busiest. Staircase and lift plaster moved ahead, and tiling and bathroom fittings continued across all three blocks.

76
Average workers on site per day
82
Most workers on a single day
7
Working days this week
Finishing
Current stage

Work this week

  • Flats: floor and bathroom tiling continued floor by floor in Blocks A, B and C.
  • Internal plaster: continued in the ground-floor flats of Block B.
  • Bathroom fittings: concealed cistern tanks and diverters being fixed in the remaining flats of Block C.
  • Lift shafts: internal plaster continued above the 1st floor.
  • Staircases: marking done and plaster started.
  • Exterior: double-coat plaster on the south face of Block A; front elevation brickwork on Block C.
  • Terrace: parapet wall plaster on Blocks A and B.
  • Clubhouse: brickwork continued.

Completed

  • Staircase marking for plaster in Block C.

Coming up next week

  • Continue internal plaster in the remaining ground-floor flats of Block B.
  • Continue staircase and corridor plaster.
  • Complete lift shaft internal plaster.
  • Continue front elevation brickwork and exterior plaster.
  • Continue tiling and bathroom fittings floor by floor.
  • Continue clubhouse brickwork.

Quality and safety

Every finished floor is checked by our site engineers before it is signed off, including tile tap-tests and level checks. Any tile that does not pass is lifted and relaid. Toolbox safety talks were held every day, and no accidents were reported.